FOREWORD
INTRODUCTION
1 Scope
2 Normative references
3 Terms and definitions
4 Symbols and abbreviations
5 Electrical power system analyses
6 Off-site power transient stability analyses
7 AC on-site power system analyses
8 DC system and uninterruptible AC system
  analyses
9 Miscellaneous analyses
Annex A (informative) - Establishment of design
        bases for nuclear power plant electrical power
        systems
Annex B (informative) - Guidelines for analytical
        studies
Annex C (informative) - Verification of design bases
        and equipment specification
Annex D (informative) - Example of plant specific
        acceptance criteria
Bibliography

Gives the electrotechnical engineering guidelines for analysis of AC and DC electrical power systems in nuclear power plants (NPPs) in order to demonstrate that the power sources and the distribution systems have the capability for safe operation and shut down of the NPP, bringing it to a controlled state after an anticipated operational occurrence or accident conditions and finally reaching a safe state.

Committee
NCE/8
DevelopmentNote
Supersedes 15/30309550 DC. (09/2016)
DocumentType
Standard
Pages
62
PublisherName
British Standards Institution
Status
Withdrawn
Supersedes

IEC 62855:2016 provides the electrotechnical engineering guidelines for analysis of AC and DC electrical power systems in nuclear power plants (NPPs) in order to demonstrate that the power sources and the distribution systems have the capability for safe operation and shut down of the NPP, bringing it to a controlled state after an anticipated operational occurrence or accident conditions and finally reaching a safe state. This standard is intended to be used:
- for verification of the design of new nuclear power plants;
- for demonstrating the adequacy and impact of major modifications of electrical power systems in operating nuclear power plants;
- and where there is a requirement to assess and establish operating limits and constraints for existing plants.

Standards Relationship
IEC 62855:2016 Identical

⚠

This standard has been withdrawn and is no longer current. No replacement edition is available.