SN EN 61954 : 1999 AMD 1 2003
Current
The latest, up-to-date edition.
POWER ELECTRONICS FOR ELECTRICAL TRANSMISSION AND DISTRIBUTION SYSTEMS - TESTING OF THYRISTOR VALVES FOR STATIC VAR COMPENSATORS
12-01-2013
1 Scope
2 Normative references
3 Definitions
4 General requirements for type and optional tests
4.1 Summary of tests
4.2 Objectives of tests
4.2.1 Dielectric tests
4.2.2 Operational tests
4.2.3 Electromagnetic interference tests
4.2.4 Production tests
4.2.5 Optional tests
4.3 Guidelines for the performance of type and
optional tests
4.4 Test conditions
4.4.1 General
4.4.2 Valve temperature at testing
4.4.3 Redundant thristor levels
4.5 Permissible component failures during type
testing
4.6 Documentation of test results
4.6.1 Test reports to be issued
4.6.2 Contents of a type test report
5 Type tests on TCR and TSR valves
5.1 Dielectric tests between valve terminals and
earth
5.1.1 AC test
5.1.2 Lightning impulse test
5.2 Dielectric tests between valves (MVU only)
5.2.1 AC test
5.2.2 Lightning impulse test
5.3 Dielectric tests between valve terminals
5.3.1 AC test
5.3.2 Switching impulse test
5.4 Operational tests
5.4.1 Periodic firing and extinction test
5.4.2 Minimum a.c. voltage test
5.4.3 Temperature rise test
6 Type tests on TSC valves
6.1 Dielectric tests between valve terminals and
earth
6.1.1 AC-DC test
6.1.2 Lightning impulse test
6.2 Dielectric tests between valves (for MVU only)
6.2.1 AC-DC test
6.2.2 Lightning impulse test
6.3 Dielectric tests between valve terminals
6.3.1 AC-DC test
6.3.2 Switching impulse test
6.4 Operational tests
6.4.1 Overcurrent tests
6.4.2 Minimum a.c. voltage test
6.4.3 Temperature rise test
7 Electromagnetic interference tests
7.1 Objectives
7.2 Test procedures
7.2.1 Switching impulse test
7.2.2 Non-periodic firing test
8 Production tests
8.1 Visual inspection
8.2 Connection check
8.3 Voltage-dividing/damping circuit check
8.4 Voltage withstand check
8.5 Check of auxiliaries
8.6 Firing check
8.7 Cooling system pressure test
9 Optional tests on TCR and TSR valves
9.1 Overcurrent test
9.1.1 Overcurrent with subsequent blocking
9.1.2 Overcurrent without blocking
9.2 Positive voltage transient during recovery test
9.2.1 Objectives
9.2.2 Test values and waveshapes
9.2.3 Test procedures
9.3 Non-periodic firing test
9.3.1 Objectives
9.3.2 Test values and waveshapes
9.3.3 Test procedures
10 Optional tests on TSC valves
10.1 Positive voltage transient during recovery test
10.1.1 Test objective
10.1.2 Test values and waveshapes
10.1.3 Test procedures
10.2 Non-periodic firing test
10.2.1 Objectives
10.2.2 Test values and waveshapes
10.2.3 Test procedures
Figure 1 - TSC branch
Figure 2 - One-loop overcurrent
Figure 3 - Two-loop overcurrent
Table 1 - List of type tests and operational tests
Annex ZA (normative) Normative references to international
publications with their corresponding
European publications
Describes type, production and optional tests on thyristor valves used in thyristor controlled reactors (TCR), thyristor switched reactors (TSR) and thyristor switched capacitors (TSC) forming part of static VAR compensators (SVC) for power system applications.
DocumentType |
Standard
|
PublisherName |
Swiss Standards
|
Status |
Current
|
Standards | Relationship |
NBN EN 61954 : 2011 AMD 1 2013 | Identical |
NF EN 61954 : 2012 AMD 2 2017 | Identical |
BS EN 61954 : 2011 | Identical |
IEC 61954:2011+AMD1:2013+AMD2:2017 CSV | Identical |
I.S. EN 61954:2011 | Identical |
EN 61954:2011/A2:2017 | Identical |
DIN EN 61954 : 2018 | Identical |
Access your standards online with a subscription
Features
-
Simple online access to standards, technical information and regulations.
-
Critical updates of standards and customisable alerts and notifications.
-
Multi-user online standards collection: secure, flexible and cost effective.